Migration of resource plans, operational resource plans, and cost plans
Summarize
Summary of Migration of Resource Plans, Operational Resource Plans, and Cost Plans
This guide outlines the process for migrating resource plans, operational resource plans, and cost plans to resource assignments and attribute-based labor costs within the ServiceNow Project Workspace. This migration simplifies project management and enhances resource allocation efficiency.
Show less
Key Features
- Migrate Resource Plans: Resource plans are converted to resource assignments based on primary attributes like Group, Skill, and Role, excluding plans in Canceled or In-progress states.
- Operational Resource Plans Migration: Similar to resource plans, operational resource plans in Allocated and Completed states are migrated to operational resource assignments.
- Cost Plans Migration: Financial cost plans associated with resource plans are migrated to new attribute-based labor costs, analyzed based on Employee Type, Expense Type, and Role.
Key Outcomes
By migrating resource plans and cost plans, you can:
- Efficiently manage resource allocations and project financials using Project Workspace.
- Enable attribute-based resource assignments for precise resource management.
- Recalculate resource costs as needed based on updates to rate models.
- Activate a scheduled job to automate the migration process for future projects and demands.
Effortlessly migrate resource plans to resource assignments and the associated cost plans to attribute-based labor costs of your projects or demands and easily work on resource allocations using Project Workspace.
Resource plans to resource assignments
Migrate all the resource plans of a project or demand to attribute-based resource assignments depending on the planning attributes to easily manage your projects on Next experience using Project Workspace and Capacity Planning.
| Resource plan status | Resource assignments status |
|---|---|
| Planned or Requested | Unassigned |
| Allocated | Approved |
| Confirmed | Approved |
| Completed | Approved |
| Cancelled or In-progress | Resource plan is not migrated |
| Rejected | Unapproved |
When a resource plan is migrated, a corresponding resource assignment is created based on the primary attributes from the resource plan. Resource assignments do not support custom selection of allocation type and allocation spread.
- Resource plans in Planning or Requested states, resource assignments are created based on the planned dates and planned duration with their default state as Unassigned.
- Allocation type is set to planned duration.
- Allocation spread is always Even.
- Existing resource allocations are deleted and created again to accommodate resource allocations with the resource name and planned duration.
- The allocated costs and allocated hours are copied to planned costs and planned hours.
- Actual hours for the resource plans in Confirmed and Allocated states are retained with the resource plans.
Migration of Resource plans to Resource assignments
Resource plans in different states.
Operational resource plans to operational resource assignments
After migration, the Request type of operational resource plans is changed to Hours.
Migration of Operational resource plans to Operational resource assignments
Operational resource plan in Allocated state created for Demo GroupA.
Migration of cost plans to attribute-based cost plans
When resource plans of a project or demand are migrated to resource assignments, the corresponding financial cost plans based on the resource plans will be migrated to new attribute-based labor costs. Migrate resource plans related link trigger migrates the cost plans along with resource plans migration.
Every resource plan has an associated a cost plan with Labor capex as the cost type. While migrating, the planning attributes of the resource plans are analyzed to create attribute-based cost plans for the unique combination of the three planning attributes enabled for financials (Employee type, Expense Type, and Role). After migration, there will be no one-to-one association between resource assignments and attribute-based cost plans.
The planned costs are moved to the new attribute-based cost plans while the actual costs remain on the existing cost plan records. The rate model values associated with project or a demand are considered to generate attribute-based labor costs.
Migration of cost plans to attribute-based cost plans
Cost plans associated to a resource plan.
Attribute-based cost plan Resource_Internal_Capex is created after migration.