Confirm a resource plan

  • Release version: Washingtondc
  • Updated February 1, 2024
  • 1 minute to read
  • As a resource manager, you can confirm or block the resources after a resource plan is requested. The resource plan must be in the Requested state to be confirmed.

    Before you begin

    Role required: resource_manager

    About this task

    You can modify or cancel a resource plan that is in the Confirmed state.

    For a resource plan with the resource type as group, you can confirm resources only if the specified group has active members.

    Note:
    You can also confirm resource plans from the Allocation Workbench.

    Procedure

    1. Navigate to All > Resource > Resource Plans > Requested.
    2. Open the resource plan that you want to confirm and select Confirm.

    Result

    The resource plan moves to the Confirmed state and soft allocations are created.