Use the Financials tab in Project Workspace to capture the
costs and benefits of a project.
Before you begin
Role required: it_project_manager
About this task
The Financials tab provides a
detailed breakdown of the cost components of a project. The total planned cost, budget
cost, actual cost, and planned returns with their breakdowns are displayed in the form
of read-only cards, while the cost plans, benefit plans, and their breakdowns are
provided in an editable grid view. Using the grid view, you can:
- Group the plan level columns; configure, sort, expand, collapse, and freeze
both the plan level and breakdown columns.
- Inline edit the breakdown values of a cost plan or benefit plan without
opening the plan in a form. Inline edit is available only in the Monthly
view.
- Create a cost plan and benefit plan for the project.
Procedure
-
Open the required project in project
workspace.
-
Click the Financials tab.
-
To create a cost plan:
-
Select Cost Plans from the list.
-
Click New.
-
To create a monetary benefit plan:
-
Select Monetary Benefit Plans from the
list.
-
Click New.
-
To view the project costs and financial breakdown summary of a project for the
selected fiscal year, select Overview from the list.
The
Overview tab gives the financial summary for
Planned Cost, Actual Cost, Variance (Planned vs Actual cost), Estimate At
Completion, and Estimate To Completion.
Note: If a project has a sub-project with
a cost plan, the financials overview breakdown view is not enabled by
default. To enable this view, a user with the it_pps_admin role should set
the value of the com.snc.project.rollup.cost property
to true.
- Optional:
Review additional fields, view plan details, or reorganize the comparative data
on the form.
- To create a baseline or compare the available baselines, click the baseline information icon (
) and then select Create New Baseline or Compare Baselines option, respectively.In the Financial Baseline comparison screen, the top two rows show all the
values in either functional currency or project currency. To display the values in project currency, click the configuration icon (
) and toggle the Show Widgets in Project Currency view.
The Financial Baseline Details pane indicates the Functional Currency and the Project Currency that has been selected.
The Financial
Baseline grid shows the Functional cost, Cost in Project currency, Actuals, and Actuals in Project Currency. You can view the Project currency at the grid level. This view is helpful when there are cost plans of
sub-projects that are in different project currency.
- To view a cost plan or benefit plan details on a form, click the information icon (
) available in the Name column of the grid.
- To view a cost plan or benefit plan details in yearly, quarterly, or
monthly format, click the Year,
Quarter or Month
views respectively.
- To toggle viewing the widgets in the Financial Summary section, click the widgets icon (
) and then select the Show Widgets option.Select an individual widget name to display the widget. Clear the selection to hide the widget.
The selected field preferences are
saved and are available when you reopen the Financial tab.
- To show or hide columns in the grid, click the configuration icon
(
) and select the field names.You cannot hide the grouped
columns. To reset to the default grid column layout, select the
Reset to defaults option.
- To view the project costs in project currency, click the configuration icon (
) and select the five widgets to show project currency amounts. The widgets are Total Planned Cost in Project Currency, Budget Cost in Project Currency, Actual Cost in Project Currency, Planned Return in
Project Currency, and Benefit in Project Currency.You can view both the functional and project currencies in the currency indicator.
In the Financial Summary grid view of the Cost
Plans and Benefit Plans tabs, all items related to project currencies are configured in the column heads such as Cost in project currency,
Project currency, and Total actual cost in project currency.
By default, you can view only the functional currency columns. To view the project currency
columns, click the configuration icon (
) and select the project currency column check boxes in the item columns.
The aggregated amount in the Cost in project currency field is clear if there are cost plans of
sub-projects with different project currency.