Managing financials for your projects
Summarize
Summary of Managing Financials for Your Projects
This guide outlines how to effectively manage project financials within ServiceNow's Project Portfolio Management module. You will learn to handle budgets, cost plans, and actual expenses, allowing for comprehensive tracking and analysis of financial performance in the Project Workspace. Key functionalities include forecasting, generating labor costs, creating financial baselines, and exporting financial data for stakeholder review.
Show less
Key Features
- Cost View: Track and manage planned costs and actual expenses across all project levels. Utilize a consolidated view for parent projects, allowing for seamless oversight of sub-projects.
- Baseline View: Create and compare financial baselines to capture and analyze financial changes, enabling project managers to monitor financial health effectively.
- Budget Allocation: Portfolio managers can plan and approve budgets at various intervals (monthly, quarterly, yearly) using lean budgeting principles to optimize financial planning.
- Simple Financials: Enter preliminary high-level financial data without the need for detailed cost plans, offering flexibility until actual costs are captured.
- Export Functionality: Share financial data by exporting it as Excel or CSV files, facilitating communication with stakeholders.
Key Outcomes
By leveraging these features, ServiceNow customers can achieve:
- Enhanced visibility and control over project financials, enabling informed decision-making.
- Improved accuracy in tracking and forecasting costs, leading to better project budget management.
- Streamlined processes for budget approval and expense line management, fostering collaboration between project and portfolio managers.
- Efficient financial reporting through easy data export options, improving stakeholder engagement and transparency.
Overall, effectively managing project financials through ServiceNow enables organizations to optimize resource allocation, minimize variances, and ensure the successful execution of projects within budget constraints.
Manage budget, cost plans as forecasts, actual expenses as expense lines, generate labor costs, create financial baselines, and view, analyze, and compare the financial performance of your projects at required cadence in Project Workspace.
The comprehensive financials view helps you to understand planned and actual costs, Estimate At Completion (EAC), Estimate To Completion (ETC), total actuals to date, and so on, for the selected entity. You can manage cost plans and associate processed expense lines to reflect the actuals for a planning item.
Export the financials data from Cost or Baselines comparison view as Microsoft Excel or a CSV file and share it with your stakeholders to review the financial performance of your projects and portfolio.
Cost view
Forecast your planned costs, create and manage cost plans and expense lines to track the financial performance of your projects, review the latest costs and actuals.
- As a Project Manager, you have the enhanced visibility and ability to manage the financial data across multiple project levels. Cost view of financials shows cost plans and expense lines from sub-projects, allowing you to track the finances.
- The parent project widgets display the consolidated values of forecasted costs and expenses.
- Identify and manage costs using the Project/Demand column for any sub project or demand directly from Cost view of the parent planning item.
- Re-forecast all the cost plan values for future fiscal periods by double-clicking to edit the value in the least time scale view, either by month or by period.
- Manage cost plans for your projects. For more information, see Add, edit, or delete cost plans.
- Add or edit expense lines for your projects to record any planned or unplanned expenses. For more information, see Add or edit expense lines.
- Generate labor costs for the fiscal period. For more information, see Generate labor costs.
- Create and compare baselines to capture the financial snapshot of your projects. For more information, see Create and compare financial baselines for your projects.
- Configure widgets to get a high-level overview of the financial data for your planning item.
- All financial details from sub-projects will be aggregated and displayed in the parent project's cost plans and widgets.
Baseline view
Create a baseline to capture a snapshot of the financial changes for your projects. You can create on-demand baselines or at a cadence using a scheduler job.
When you create a financial baseline for a parent project, the financial records of the child project are also calculated, which helps Project Managers to track the financial health of the projects at one place.
The baselines comparison view helps you to understand the variances between the two baselines.
- Two dedicated widgets for each baseline displaying the EAC.
- Third widget displays the total variance between the EAC values of the selected baselines.
- Fourth widget displays the top three variances contributing to the overall variance by cost type.
When you compare baselines, you get the list of cost plans with their associated costs types, EAC at full scope, and a breakdown view of actual expenses and planned costs.
- Use the Time scale option to view the comparison breakdown view at monthly, quarter, and yearly levels.
- Select Time scope to filter fiscal periods, data in the widgets, and the comparison table.
- Fourth widget displays the top three variances contributing to the overall variance by cost type.
Let's take an example of the comparison view of two baselines: 2023-10-01, Baseline A, and Current Financials, Baseline B.
When you compare baselines, you get the list of cost plans with their associated costs types, EAC at full scope, and a breakdown view of actual expenses and planned costs.
By default, the time scale of the breakdown view is set to Month.
When you compare baselines, you get the list of cost plans with their associated costs types, EAC at full scope, and a breakdown view of actual expenses and planned costs.
How actuals, planned, and EAC are compared between two baselines captured at different timestamps
For a selected baseline, based on the creation date, the table shows Actuals values for the past fiscal periods from the created date and Planned values for the current and future fiscal periods.
- The baseline comparison view show Actuals vs Actuals columns from July 2023 to September 2023.
- Planned vs Actuals for October 2023 and November 2023.
- Planned vs Planned from December 2023 to June 2024.
Budget allocation
Portfolio managers can manage and approve the budget for projects. The approved budget helps project managers to plan and meet the expenses to execute work.
Choose the cost type as the attribute to allocate and approve the budget for individual cost types such as labor, non-labor.
Project managers can view the approved budget at the required time scale by enabling the Budget vs cost () toggle in Cost view. As the work progresses and the actuals are captured, you can compare the budget and actual costs from the Budget vs cost view and reforecast the planned costs where the actuals
are exceeding the budget using the inline edit feature at the required time scale.
Product managers can compare the latest cost with the approved budget by Capex or Opex, cost types, and for the required time scale at monthly, quarterly, or yearly level. The comparison view provides insights to Product managers to locate any variance at expense type or cost type, and at which fiscal period. Product manager can leverage this information to request for additional budget from the Portfolio manager.
Simple financials
Simple financials gives you the ability to enter the preliminary high-level planned capex, opex, benefit and so on from the Details page without capturing the costs plans from the Cost view. You can update the simple financials values as required until you have the planned and actual costs captured.
- Reforecast simple financials and compare the by selecting the Current Financials from the list of baselines.
- Capture the planned and actual expenses as the project progresses and compare any financial baseline with simple financials baseline to track the financial performance of the project.