Reduce the duration of a resource plan
Reduce the duration of an allocated or confirmed resource plan and deallocate resources in one action without having to do it individually for each resource.
Before you begin
Role required: resource_manager
About this task
You can reduce an allocated or confirmed resource plan only if the resource plan's end date is later than the current date.
You can reduce the duration of an operational resource plan only if its state is allocated.
Procedure
Result
- The end date of the resource plan is updated to the new reduced end date.
- The state of the resource plan remains the same.
- If no actuals are posted for the future in the resource plan, all allocated or confirmed hours of the resources are released.
- If actuals are posted for the future, then the resource plan end date is updated to the future date on which actuals are present, and all the allocated or confirmed hours of all the resources from the date on which actuals are present to the original end date are released.