Migration of resource plans, operational resource plans, and cost plans
Summarize
Summary of Migration of Resource Plans, Operational Resource Plans, and Cost Plans
This process focuses on migrating resource plans and cost plans to optimized resource assignments and attribute-based labor costs within your projects or demands. Utilizing Project Workspace, you can effectively manage resource allocations and project financials. Resource Managers are encouraged to participate in the Resource Management Workspace boot camp for deeper insights into this migration process.
Show less
Key Features
- Resource Plans to Resource Assignments: Migrate your resource plans to attribute-based resource assignments based on primary attributes such as Group, Skill, and Role. Only resource plans in specific states (Planned, Requested, Confirmed, Allocated, and Completed) will be migrated.
- Status Mapping: The migration aligns the status of resource plans to corresponding resource assignments, ensuring clarity in tracking (e.g., Planned or Requested becomes Unassigned).
- Operational Resource Plans: Similar migration logic is applied to operational resource plans, transitioning them into operational resource assignments while retaining parent-child mapping.
- Cost Plans to Attribute-Based Cost Plans: When migrating resource plans, associated cost plans are transformed into attribute-based labor costs, considering attributes like Employee Type, Expense Type, and Role.
Key Outcomes
- You can efficiently manage resource allocations and project financials using the new attribute-based resource assignments and cost plans.
- After migration, the system will provide a consolidated view of costs associated with resource assignments, although actual costs will remain on existing records.
- It is essential to activate the scheduled job to facilitate the migration process for both resource and cost plans.
Migrate resource plans to resource assignments and the associated cost plans to attribute-based labor costs of your projects or demands and easily work on resource allocations using Project Workspace.
Resource plans to resource assignments
Migrate all the resource plans of a project or demand to attribute-based resource assignments depending on the planning attributes to easily manage your projects on Next experience using Project Workspace and Capacity Planning.
| Resource plan status | Resource assignments status |
|---|---|
| Planned or Requested | Unassigned |
| Allocated | Approved |
| Confirmed | Approved |
| Completed | Approved |
| Canceled or In-progress | Resource plan isn’t migrated |
| Rejected | Unapproved |
When a resource plan is migrated, a corresponding resource assignment is created based on the primary attributes from the resource plan. Resource assignments don’t support custom selection of allocation type and allocation spread.
Resource assignments only support even spread of resource allocations by default.
- Resource plans in Planning or Requested states, resource assignments are created based on the planned dates and planned duration with their default state as Unassigned.
- Allocation type is set to planned duration.
- Allocation spread is always Even.
- Existing resource allocations are deleted and created again to accommodate resource allocations with the resource name and planned duration.
- The allocated costs and allocated hours are copied to planned costs and planned hours.
- Actual hours for the resource plan in Confirmed and Allocated states are retained with the resource plans.
Migration of Resource plans to Resource assignments
Resource plans in different states.
Operational resource plans to operational resource assignments
After migration, the Request type of operational resource plans is changed to Hours.
Migration of Operational resource plans to Operational resource assignments
Operational resource plan in Allocated state created for Demo GroupA.
Migration of cost plans to attribute-based cost plans
When resource plans of a project or demand are migrated to resource assignments, the corresponding financial cost plans based on the resource plans will be migrated to new attribute-based labor costs. Migrate resource plans related link trigger migrates the cost plans along with resource plans migration.
Every resource plan has an associated a cost plan with Labor capex as the cost type. While migrating, the planning attributes of the resource plans are analyzed to create attribute-based cost plans for the unique combination of the three planning attributes enabled for financials (Employee type, Expense Type, and Role). After migration, there will be no one-to-one association between resource assignments and attribute-based cost plans.
The planned costs are moved to the new attribute-based cost plans while the actual costs remain on the existing cost plan records. The rate model values associated with project or a demand are considered to generate attribute-based labor costs.
Migration of cost plans to attribute-based cost plans
Cost plans associated with a resource plan.
Attribute-based cost plan Resource_Internal_Capex is created after migration.