SAFe Sprint Dashboard
Summarize
Summary of SAFe Sprint Dashboard
The SAFe Sprint Dashboard helps ServiceNow customers track and forecast the progress of SAFe stories within the current sprint. It provides critical insights into sprint completion status, scope changes, and team performance to support timely delivery and sprint goal achievement.
Show less
Key Features
- Sprint Progress Indicators: Displays percentage of work completed, time elapsed in the sprint, and the number of stories missing estimates to ensure accurate tracking.
- Scope and Story Status: Shows the planned scope in story points, current progress of stories by state, and scope changes with trends for dynamic sprint management.
- Forecasting: Predicts sprint completion likelihood and scope changes based on historical data, enabling proactive adjustments by the team.
- Widgets and Reports: Includes visualizations such as Sprint Burndown, Sprint Burnup, and Sprint Cumulative Flow Diagram to monitor work remaining, completed, and flow through states.
- Customizable Reports: Customers can tailor Burnup, Burndown, and Cumulative Flow Diagram reports to fit their specific tracking requirements.
Key Outcomes
- Enhanced Sprint Visibility: Scrum masters and SAFe users gain real-time insights into sprint progress, time management, and bottlenecks to keep work on track.
- Improved Forecast Accuracy: Story point-based metrics and forecasting tools help predict if the sprint will finish on time and within scope.
- Informed Decision Making: By analyzing scope changes and story states, teams can adjust priorities and resources promptly to meet sprint goals.
- Ensured Data Integrity: Emphasis on story estimation ensures meaningful reporting; if estimates are missing, default values can be used to maintain dashboard functionality.
End Users and Roles
The primary users are SAFe scrum masters, who review sprint burndown trends, resolve bottlenecks, and guide the team to complete work on schedule. The required role to access and use the dashboard is safescrumuser.
Track the progress of your SAFe stories in the current sprint and forecast sprint completion using the SAFe Sprint Dashboard.
- Displays important details of the sprint such as percentage of work that is complete, time elapsed, and total number of stories that are missing estimates.
- Displays the number of stories of the sprint in their current state and their progress.
- Indicates the scope changes, if any, and trends of those scope changes.
- Indicates how the team needs to progress on stories to achieve the sprint goal.
- Forecasts data showing the likelihood of completing the sprint as planned.
End user and roles
| End user and goal | Required role | Benefits |
|---|---|---|
SAFe scrum master: Reviews the sprint burndown trends. Resolves any bottlenecks and targets to complete the sprint on time. |
safe_scrum_user |
|
Indicators
- SAFe: Sum of story points of all stories in the current sprint
Generates the scope series in the Sprint Burndown report. The scope series indicates the amount of work in story points that is planned for the sprint.
- SAFe: Sum of story points of active stories in the current sprint
Generates the actual burndown series in the Sprint Burndown report. The actual burndown series indicates the amount of work left (in story points) for completion.
- SAFe: Sum of story points of completed stories in current sprint
Generates the percentage of stories completed for the current sprint.
- SAFe: Time elapsed in sprint
Calculates the time to be displayed in the Time Elapsed widget.
- SAFe: Count of stories in the current sprint
Generates the area series in the Sprint Cumulative Flow Diagram report. It indicates the number of stories in the current sprint.
Breakdowns
- SAFe: Sprint
- SAFe: Current Sprint
- SAFe: State
Widgets
- Scope
Indicates the amount of work in story points that is planned for the sprint. This widget lets you see at a glance how much work must be completed to achieve the sprint goal. It also lets you drill down to detail on the stories planned into the sprint.
- Percent Completed
Indicates the percentage of work that has been completed in the sprint using story points. This widget lets you see at a glance how much work has been completed in the sprint. Together with the adjacent Time Elapsed widget, these widgets lets you easily see whether you are completing work at a rate consistent with achieving the sprint goal on schedule.
- Time Elapsed
Indicates the percentage of time that has elapsed between the start date and planned end date of the sprint. Together with the adjacent Percent Completed widget, these widgets let you easily see whether you are completing work at a rate consistent with achieving the sprint goal on schedule.
- Committed Points
Indicates the committed scope (in number of story points) of the sprint. Together with the adjacent Scope widget, these widgets let you see difference between the scope committed at the start of the sprint and the current scope of the sprint.
Note:This widget is not visible by default. You can add it from Reports to your dashboard. For more information, see Edit a responsive dashboard.- Blocked Work
Indicates the amount of work (in story points) in the sprint that is blocked.
- Stories Missing Estimates
- Indicates the total number of stories in the sprint that are missing estimates. It is required that you use estimates for the other indicators, widgets, and reports on this dashboard to be meaningful.Note:If you do not estimate stories, enter a "1" in the Story Points field. The other indicators, widgets, and reports will then effectively function by count.
Data visualizations
- Sprint Burnup
- Sprint Cumulative Flow Diagram
| Title | Type | Description |
|---|---|---|
| Sprint Burndown | Line chart |
Indicates the scope changes, if any, and trends of those scope changes. Indicates the
ideal pace of work, how much work is remaining, and if the scope is likely to be completed
before the end of the sprint. The Sprint Burndown report comprises the following series
that can be hidden or displayed based on your preference:
|
Sprint Burnup |
Line chart |
Shows the sprint burnup trend indicating scope changes. Forecasts future changes in scope and the trend of work completion. The Sprint Burnup report comprises the following series that can be hidden or displayed
based on your preference:
|
Sprint Cumulative Flow Diagram |
Area chart |
Monitor the progress of all the stories of your sprint between its actual start and end dates. View the number of stories in each state by their arrival to a state, time in this state, and its departure from this state. The Sprint Cumulative Flow Diagram report comprises the following areas that can be
hidden or displayed based on your preference:
Note: Stories in Ready and Cancelled states are not included in this report. |
You can customize the Burnup, Burndown, and Cumulative Flow Diagram reports. For more information, see Customizing Essential SAFe dashboard reports.