Planned work schedules mainly run using the Planned Maintenance Nightly
Run scheduled job. However, you can make the schedule to run immediately or
change the date when a schedule should run, if needed.
Before you begin
Role required: admin
About this task
When you run a planned work schedule on demand, all of the
next run dates for the relevant planned work records are updated to the user-defined
time, now or in the future. All the appropriate work orders are created. If the schedule
is meter, condition, or script-based, work orders are created for work plan records that
meet the schedule criteria.
Procedure
-
Navigate to .
-
Open a work plan that contains the schedule to run.
-
In the Planned Work Schedules related list, select the maintenance schedule you
want to run.
-
In the Related Link section, click Run on demand.
-
On the form, fill in the fields.
Table 1. Run Maintenance On Demand form
| Field |
Description |
| Run now |
Option to run the maintenance for the schedule
immediately. |
| Select next run date |
Date in the future for maintenance to run. This field
appears only when the Run now
option is not selected. |
-
Click Schedule.