Load data from Watershed into Operational Sustainability Management

  • Freigeben Version: Australia
  • Aktualisiert 12. März 2026
  • 1 Minute Lesedauer
  • Load data from the Watershed spreadsheets into the staging table. After you load the data and complete the setup, you can start using the Operational Sustainability Integration with Watershed.

    Vorbereitungen

    You must add the import_admin role to the sn_grc_metric.admin role.

    Role required: sn_esg.program_manager

    Prozedur

    1. Navigate to All > Operational Sustainability Management > Load Data.
    2. On the Load Data form, select Existing table.
    3. In the Import set field, select Watershed Data [sn_esg_watershed_data].
    4. Select Choose File, and select the file that you want to load.
    5. Select Open.
    6. In the Sheet number field, verify that the sheet number is appropriate.
    7. In the Header row field, verify that the header row is appropriate.
    8. Select Submit.

    Ergebnisse

    The spreadsheet is loaded in the staging table. All the columns from the spreadsheet are created.

    Nächste Maßnahme

    View the import set.