# Calculating RTO and RPO

# Calculating RTO and RPO {#ariaid-title1}

Release version: Zurich  
Updated July 31, 2025  
![](https://www.servicenow.com/docs/portal-asset/ico-clock) 6 minutes to read
Summarize  
![AI sparkle icon](https://servicenow.com/docs/portal-asset/ai-sparkle-icon) Summarized using AI  
This content was generated using new OpenAI-powered functionality. Results are provided on an as is basis and are not guaranteed to be accurate or complete.  

## Summary of Calculating RTO and RPO

The Business Continuity Management (BCM) application in ServiceNow enables customers to calculate the Recovery Time Objective (RTO) and Recovery Point Objective (RPO) during the Business Impact Analysis (BIA).
These calculations are based on assessment questionnaires configured by BCM administrators.
The process helps organizations determine acceptable downtime and data loss thresholds to support effective business continuity planning.
Show full answer Show less  

## Key Features

* **Assessment Questionnaire Setup:** BCM administrators define impact categories and ratings (e.g., Low, Moderate, High) with associated disruption durations and tolerability thresholds. This setup drives the calculation logic for RTO and RPO.
* **BIA Workflow Integration:** BIA owners and IT analysts respond to tailored assessment questions within the BCM Workspace. Their inputs on business services, processes, and IT systems inform the RTO and RPO estimates.
* **RPO Calculation:** The application calculates the RPO by selecting the highest impact category score from assessment responses and mapping it to a timeframe (e.g., "Immediately") using template-defined score thresholds.
* **RTO Calculation:** The RTO is determined by identifying the lowest "Tolerable downtime" value across all impact categories based on the highest non-tolerable disruption durations. If all ratings are tolerable, a maximum RTO value from the template is used.
* **Dynamic Updates:** Changes to disruption durations in impact categories automatically recalculate the overall BIA RTO, ensuring ongoing accuracy.
* **Recovery Tier Assignment:** The recalculated RTO maps to a predefined recovery tier (e.g., Mission Critical, Business Critical) that reflects the organization's recovery priorities and timelines.

## Practical Application for ServiceNow Customers

By leveraging the BCM application's structured approach to configuring impact ratings and capturing assessment responses, customers can:

* Systematically evaluate the maximum allowable downtime and data loss for critical business functions.
* Ensure that recovery objectives align with organizational risk tolerance and regulatory requirements.
* Automate the calculation of RTO and RPO to support consistent and repeatable business continuity planning.
* Use recovery tiers linked to RTO values to prioritize restoration efforts and resource allocation during disruptions.

This functionality supports comprehensive business impact analysis and helps organizations prepare effective recovery strategies based on quantifiable objectives.  
The BCM application provides an assessment questionnaire for calculating the recovery time objective (RTO) and recovery point objective (RPO) in the business impact analysis (BIA). As a pre-requisite
to the BIA, BCM administrator defines the impact ratings and sets up the assessment questions. After receiving the responses to the assessment, the BCM application calculates the RTO and RPO.

## BCM dependency tree {#rto-rpo-calculation__section_tgd_j23_s2c}

Before calculating the recovery time objective (RTO) and recovery point objective (RPO) in the business impact analysis (BIA), verify that all the required BCM applications are installed.

## BCM implementation {#rto-rpo-calculation__section_hvh_g23_s2c}

Setting up the impact ratings to evaluate an impact category is a crucial step in business continuity management. To grasp the importance of configuring these impact categories, refer to the steps needed for implementing the BCM process, as outlined in the checklist.  
Figure 1. Graphical flowchart of BCM implementation checklist

BIA workflow

:   When a BIA owner submits the BIA for review, the BIA moves to the review state. The BIA owner responds to questions in the assessment questionnaire. IT analysts and IT owners can estimate the recovery point objective for data
    applications and systems. To do so, respond to the Recovery point objective assessment in the BIA. Based on the BCM administrator configuration, questions appear in the Recovery point objective assessment tab
    of the BIA.

    A sample BIA workflow is shown in the example.

## Responding to the assessments {#rto-rpo-calculation__section_kyg_4vt_zxb}

The business users and IT owners perform business impact analysis by responding to the assessments in the BIA component in the BCM UIB Workspace. A sample view of the Assessments tab is shown in the example.

IT owners can estimate the recovery point objective for data applications and systems. Respond to the Recovery point objective assessment in the BIA.

## Administrator view for configuring impact category and ratings {#rto-rpo-calculation__section_m22_l12_3xb}

BCM administrators configure the assessment questionnaire to include one or more impact ratings such as Low, Moderate, or High for an impact category. The Impact
Ratings related list is displayed in the Impact Category record as shown in the example.  
BCM administrators specify the threshold of non-tolerance for the impact ratings according to impact category. The disruption duration for the first non-tolerable impact category is selected for the recovery time objective (RTO). The impact ratings have the specified values:

* Low = 1
* Moderate = 2
* High = 3
{#rto-rpo-calculation__ul_f14_4r2_3xb}  
The rating for the impact category is calculated based on the disruption duration as shown in the example.Figure 2. Calculating the impact category

Based on the configuration set up by BCM administrator, the questions are displayed in the Recovery point objective assessment tab as shown in the example.

## Calculation of RPO score for the BIA with examples {#rto-rpo-calculation__section_wdz_nrh_s2c}

Consider the scenario where each question response has a numeric value. The application calculates the category score for each RPO impact
category based on the highest response value.

The application selects the highest category score from all the RPO categories. In the example, the highest category score is 40.

The application uses the Score Timeframe Mapping, defined at the template level, to determine the appropriate timeframe value. In the example, the category score is 40, which falls between the lower and upper threshold scores.
The timeframe mapped to this score is "Immediately." Therefore, the system-calculated RPO value is "Immediately."

## Recovery time objective assessment {#rto-rpo-calculation__section_amq_jzd_3xb}

As a business user, you can estimate the recovery time objective for your business services and processes. Respond to the Recovery time objective assessment in the Assessments tab. Questions appear in the
Recovery time objective assessment tab based on the configuration set up by BCM administrators. The following example shows a sample assessment.

## Calculation of RTO score for the BIA with examples {#rto-rpo-calculation__section_czk_s5h_s2c}

Consider the scenario where each question response is assigned a numeric value. The application identifies the highest tolerable value for each
RTO Impact category.

The application calculates the "Tolerable downtime" value for each RTO Impact category as the Impact rating with a value higher than the highest tolerable value. If no value exists, it uses the maximum RTO value defined
at the Impact category.

The RTO score is the lowest "Tolerable downtime" value across all RTO impact categories.  
Note:  
RTO cannot be calculated when the recovery tier doesn't exist for the "Tolerable downtime" value.

In the example, the RTO score based on the lowest "Tolerable downtime" value is 8 Hours.

## Sample RTO calculation {#rto-rpo-calculation__section_nkp_dlt_zxb}

Consider the scenario for another sample RTO calculation. BCM administrator has configured an intolerable impact rating for the Revenue impact category and defined the intolerable impact. If you are the business impact analysis owner, you must identify the timeline at which the revenue impact may go beyond $1M. See the sample RTO calculation for different scenarios as shown in the table.{#rto-rpo-calculation__table_zsm_2y2_3xb__entry__3}

| Scenario | Non-tolerable impact | Description |
|-|-|-|
| Scenario 1 | In the Impact Ratings table, the Tolerable field is set to false. | If the administrator has specified that Low regulatory impact is non-tolerable, its corresponding disruption duration is set as the recovery time objective (RTO). In this example, the disruption duration for the 01 - Low impact rating is set to 4 hours. Therefore, the recovery time objective (RTO) for the impact category is above 4 hours. Even if the moderate impact disruption duration is shorter, the calculation selects the value from the first alphanumerically sorted impact rating that has the Tolerable field set to false. |
| Scenario 2 | In the Impact Ratings table, the Tolerable field is set to false. | If the administrator has specified that Moderate regulatory impact is non-tolerable, its corresponding disruption duration is set as the recovery time objective (RTO). In this example, the disruption duration for 02 - Moderate impact is set to 24 hours. Therefore, the recovery time objective (RTO) for the impact category is above 24 hours. |
| Scenario 3 | In the Impact Ratings table, the Tolerable field is set to false. | If the administrator has specified that High regulatory impact is non-tolerable, its corresponding disruption duration is set as the recovery time objective (RTO) as shown in the example. In the tabular example, the disruption duration for 03 - High impact is set to 72 hours. Therefore, the recovery time objective for the impact category is above 72 hours. |
| Scenario 4 | The Tolerable field for the Low, Moderate, and High impact ratings is set to true. | If the administrator has set all the impact ratings as tolerable, the value specified in the Maximum RTO value field in the template is selected as the recovery time objective (RTO). In the example, the administrator has set all the impact ratings as tolerable. Therefore, the recovery time objective (RTO) is one month according to the value specified in the Maximum RTO value field. |
[Table 1. Sample scenarios]

{#rto-rpo-calculation__table_zsm_2y2_3xb}

Calculation of overall impact assessment result for a BIA

:   When you update the Disruption Duration of an impact category, the RTO of the BIA is automatically updated. The RTO of the BIA is set as the lowest tolerable downtime from each impact category.

    For example, consider a BIA with four impact categories: Legal, Reputation, Workforce, and Regulatory. When you update the disruption duration of the Legal impact category, the RTO of the BIA is recalculated. The recalculated RTO
    reflects the lowest tolerable disruption duration across all impact categories. The Recovery Tier is set based on the recalculated RTO and varies by organization.  
    {#rto-rpo-calculation__table_wm3_ccw_xmb__entry__2}

    | RTO value | Recovery Tier |
    |-|-|
    | Immediate | Mission Critical |
    | 1 Hour | Mission Critical |
    | 4 Hours | Mission Critical |
    | 8 Hours | Business Critical |
    | 24 Hours | Business Critical |
    | 72 Hours | Essential |
    | 1 Week | Essential |
    | 2 Weeks | Non-Essential |
    | 1 Month | Non-Essential |
    [ ]

    {#rto-rpo-calculation__table_wm3_ccw_xmb}