# Enhancing event task management with Hierarchical view

# Enhancing event task management with Hierarchical view {#ariaid-title1}

Release version: Zurich  
Updated November 11, 2025  
![](https://www.servicenow.com/docs/portal-asset/ico-clock) 3 minutes to read
Summarize  
![AI sparkle icon](https://servicenow.com/docs/portal-asset/ai-sparkle-icon) Summarized using AI  
This content was generated using new OpenAI-powered functionality. Results are provided on an as is basis and are not guaranteed to be accurate or complete.  

## Summary of Enhancing event task management with Hierarchical view

The Hierarchical view for event tasks in ServiceNow's Zurich release has been enhanced to streamline task management through an interactive Gantt chart.
This update allows customers to visualize task dependencies, view color-coded task states, and manage timelines more effectively by displaying planned and actual start and end dates.
Show full answer Show less  

## Key Features

* **Dependency Visualization and Management:** View and manage task dependencies directly within the Gantt chart. Customers can see dependency details in a modal, create new dependencies by dragging between tasks, and delete dependencies easily. The system prevents cyclic dependencies to maintain valid project structures.
* **Color-Coded Task States:** Tasks are color-coded for quick status identification---green for all closed states, red for closed failed, grey for hold/pending, blue for open, and yellow for work in progress. Hovering over tasks reveals detailed information including state, start/end dates, and assignments.
* **Sorted Plans by Start Date:** Activated plans within the Hierarchical view are automatically sorted by their planned start dates, providing a clear, chronological overview of task sequences.
* **Planned and Actual Dates:** Both planned and actual start/end dates are available and can be toggled in the Gantt chart. This enables customers to compare scheduled timelines against real progress for better project tracking.
* **Interactive Gantt Chart:** The chart is resizable and allows expanded views of detailed information, including completed plans, enhancing usability and insight into event task progress.

## Practical Benefits for ServiceNow Customers

* Improved clarity and control over event task dependencies and timelines, reducing management complexity.
* Visual cues through color coding accelerate status recognition and prioritization.
* Direct manipulation of dependencies within the Hierarchical view streamlines workflow adjustments without navigating away.
* Ability to toggle between planned and actual dates helps monitor deviations and adjust plans proactively.
* Chronologically sorted plans facilitate better scheduling and resource allocation.  
The Hierarchical view for event tasks has been enhanced with several key features. It now displays dependencies between tasks, and shows color-coded states with planned start and end dates. Dependencies can be updated directly
through the Hierarchical view (Gantt chart), streamlining event task management.

## Sorting plans {#managing-enhanced-hierarchical-view-in-event-tasks__section_txd_pzy_ghc}

In the Hierarchical view, activated plans are now sorted by their start date. The example shows an event task with activated plan, its start date, end date, state, and so on. The
start date for the plan shown in the example is 18th.

The plans are displayed in sorted order. The example shows the next plan having a start date of the 20th.

Color-coded plans offer a visually organized view.

## Managing task dependencies in Hierarchical view (Gantt chart) {#managing-enhanced-hierarchical-view-in-event-tasks__section_vql_yzy_ghc}

To manage task dependencies, you can select View dependencies in the Dependencies column. This enhancement
enables you to view the dependencies between tasks, including the state of the dependent plan and other relevant details.

After selecting View dependencies, a modal view displays the dependency details. Details include the dependent task (for example, RT3 depends on RT2), its dependency (RT2), and the state of the dependent
plan (activated). This display provides a clear understanding of task relationships and their current status.

You can visualize and manage task dependencies directly in the Gantt view. All dependencies are clearly displayed, enabling you to understand task relationships at a glance. To delete a dependency, select the link between
tasks and press the Backspace or Delete key on the keyboard.

To create a new dependency, drag from the end of one task to the start of another task and add a link. This action establishes a dependency between the two tasks, enabling you to manage their relationship effectively. When a
dependency changes, all affected tasks' planned start times are updated accordingly.

You can create multiple links between tasks to manage dependencies directly within the Gantt chart. Cyclic dependencies are not permitted. For example, if Task 1 depends on Task 2, Task 2 cannot depend on Task 1. This prevents
invalid project structures.

## Color-coded bars {#managing-enhanced-hierarchical-view-in-event-tasks__section_of4_51z_ghc}

The bars in the chart are color-coded. Select a legend to view the color conventions for task states such as Closed complete, Closed duplicate, and Closed incomplete. This
color-coding helps identify task status quickly.  
The task states are represented by these color codes:

* Green: All "Closed" states
* Red: "Closed failed" states
* Grey: "Hold" and "Pending" states, indicating a waiting or paused status
* Blue: "Open" state, signifying that a task is open and ready for action
* Yellow: "Working progress" state, indicating that a task is in progress
{#managing-enhanced-hierarchical-view-in-event-tasks__ul_h4k_y3z_ghc}This color-coding system provides a clear visual representation of task statuses, making it easier to track progress and identify areas that require attention.

In the Gantt view, tasks are color-coded based on their status: yellow for "work in progress" and blue for "open" tasks. Hovering over a task bar displays additional information, including the task state, plan start and end
dates, and assignment details if applicable. The Planned start and Planned end dates are also introduced at the activated plan level, which are calculated based on the associated event tasks. It's shown that the planned start date is
18th and the planned end date is 21st.

In the example, the first event task begins on the 18th and concludes on the 21st. Since the second task is dependent on the first, it starts on the 21st and ends on the 24th. This dependency-based timeline calculation applies
to all subsequent tasks. The Gantt chart is interactive, enabling you to adjust its size. Selecting Show more on any activated plan enables you to view detailed information, including completed plans.

You can view the actual start and end dates in the Gantt chart. To view the dates, select the toggle and the chart gets updated to display the actual dates, providing an accurate representation of the progress of the
project.

You can toggle between viewing planned dates and actual dates using the switch button, enabling for easy comparison and tracking the progress of the project.