# Configure due dates

# Configure due dates for tasks {#ariaid-title1}

* Versão de lançamento: Australia
* 
* Atualizado 12 de mar. de 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 min. de leitura

Configure due dates for different task types so that the Due date field is auto-populated when you create tasks for internal users and suppliers.

## Antes de Iniciar

Role required: sn_slm.admin

## Por Que e Quando Desempenhar Esta Tarefa

Although the Due date field is auto-populated for a task type, you can always update this field as required.

## Procedimento

1. Navigate to AllSupplier Lifecycle OperationsAdministrationDefault Due Dates for Tasks.  
   The Decision Builder opens and displays the Decision table for configuring the default due dates.  
   {#configure-task-due-date__table_wbc_wbv_tyb__entry__2}

   | Task type | Default due date |
   |-|-|
   | Mark complete | 3 |
   | View link | 3 |
   | Play video | 3 |
   | Upload documents | 3 |
   | Complete a form | 3 |
   | Sign document | 3 |
   | Complete checklist | 3 |
   | Complete survey | 3 |
   [Tabela 1. Default due dates for task types]

   {#configure-task-due-date__table_wbc_wbv_tyb}
2. Under the Default due date column, select a row next to the task type row and enter a positive number.  
   The number that you enter for a task type is auto-populated in the Due date field the next time you create a task of that task type.

   For example, let's say that you enter 3 as the due
   date for the task type Mark complete. If you create a Mark complete task on September 12, the due date will be in three days from this date; that is, September 15.
3. Select Save.

## Resultado

The default due dates for the different task types are configured.
**Tarefas relacionadas**   

* [Create a task for a supplier case from the Source-to-Pay Workspace](https://servicenow-prod.fluidtopics.net/6QYd4lhmm8iVy6d7OJsuHA "You can create a task for a supplier case and assign it to a supplier contact.")
* [Submit a task from the Source-to-Pay Workspace](https://servicenow-prod.fluidtopics.net/yFY901hjejWOfd8zS0Gnow "Submit a task in Draft state to indicate that it is ready to be worked on.")
* [Complete a supplier task from the Source-to-Pay Workspace](https://servicenow-prod.fluidtopics.net/4QmfNeteNnXJXy8fD2Nocg "You can mark a supplier task as complete when you finish all the activities related to that task.")