Set up Planning dependency update configuration

  • Versão de lançamento: Australia
  • Atualizado 12 de mar. de 2026
  • 1 min. de leitura
  • Configure the Planning dependency update configuration record to configure the plan record (for which the dependencies are updated), its target records, sources, and notification preferences.

    Antes de Iniciar

    Role required: sn_bcm.admin, sn_bcp.plan_admin

    Procedimento

    1. Navigate to Business Continuity > General Administration > Planning dependency update configuration.
    2. Select New.

      The example shows the Planning dependency update configuration record.

      Updating the BCP dependencies.
    3. On the form, fill in the fields.

      For more information on the fields in the form, see Planning dependency update configuration form.

    4. Select Submit.

      As per the sources and preferences set up by the BCM administrator in the BCM administrator in the Planning dependency update configuration record, the planning dependency updates are auto-updated for the plan record.

      The BCP owner and approver review the updated dependencies and complete the BCP workflow.