Add external dependencies between projects from Project Workspace

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:2分
  • Set up a dependency between tasks of different projects using the new Project Workspace.

    始める前に

    Role required: it_project_manager

    このタスクについて

    External dependencies help you understand the impact on project schedules when there is a change in the predecessor task. Use the row context menu of your project task to add a dependency from the task of a different project.

    手順

    1. Open a project from the home page of Project Workspace.
      For information, see Access the new Project Workspace.
    2. From the data grid, select the project task to which you want to add the dependency.
    3. Select the row context menu (Row context menu.) of the task and select Add external dependency.
    4. On the External Dependency form, select the Project to which the external task belongs.
    5. Select the Task for which the dependency is added.
    6. Select the Dependency type.
    7. Select Submit.
      The default selection is Hard. In a hard dependency, any changes made in the predecessor project are automatically propagated to the successor project.

    タスクの結果

    • Dependency is created for the tasks of the two projects.
    • The short description of your project is greyed out and is renamed to indicate the external dependency in the format of External project name: External task name
    • A link icon (External dependency icon) is added to the short description cell of the task, to indicate the dependency.

    次のタスク

    You can navigate to the external project directly from the current project to view the status or update the details of the predecessor task. From the row context menu of the dependent task, select View project.