Project Type Fields form
Field descriptions for the Project Type Fields form. Use this reference when entering key project dates for a retail store project.
New store opening project type form fields
| Field | Description |
|---|---|
| Store go-live date | Date on which the retail store is scheduled to open and begin operations. |
| IT installation date | Date on which IT systems and technology infrastructure are scheduled to be installed at the store. |
| Site approval date | Date on which the store site receives formal approval to proceed with the project. |
| Construction start date | Date on which construction or refurbishment work at the store site is scheduled to begin. |
Store relocation project type form fields
| Field | Description |
|---|---|
| Relocation approval date | Date on which the store relocation receives formal approval to proceed. |
| Current store closure date | Date on which the current store location is scheduled to close. |
| New site readiness date | Date on which the new store site is expected to be ready for operations. |
| Relocation completion date | Date on which the relocation of the store is scheduled to be complete. |
Store refurbishment project type form fields
| Field | Description |
|---|---|
| Refurbishment approval date | Date on which the store refurbishment receives formal approval to proceed. |
| Decommissioning start date | Date on which decommissioning of the existing store setup is scheduled to begin. |
| Fit-out completion date | Date on which the store fit-out work is scheduled to be complete. |
| Re-opening date | Date on which the refurbished store is scheduled to reopen for operations. |
Store technology refresh project type form fields
| Field | Description |
|---|---|
| Refresh approval date | Date on which the technology refresh receives formal approval to proceed. |
| Installation scheduled date | Date on which the installation of new technology is scheduled to begin. |
| Installation completion date | Date on which the technology installation is scheduled to be complete. |
| Store handover date | Date on which the store is handed over after the technology refresh is complete. |
Store closure project type form fields
| Field | Description |
|---|---|
| Closure decision date | Date on which the decision to close the store is formally made. |
| Last trading day | Date on which the store is scheduled to trade for the last time. |
| Asset recovery completion date | Date on which the recovery of store assets is scheduled to be complete. |
| Closure confirmation date | Date on which the store closure is formally confirmed. |