# Load data from Watershed into Operational Sustainability Management

# Load data from Watershed into Operational Sustainability Management {#ariaid-title1}

* Release version: Australia
* 
* Updated March 12, 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 minute to read

Load data from the Watershed spreadsheets into the staging table.
After you load the data and complete the setup, you can start using the Operational Sustainability Integration with Watershed.

## Before you begin

You must add the import_admin role to the sn_grc_metric.admin role.

Role required: sn_esg.program_manager

## Procedure

1. Navigate to AllOperational Sustainability ManagementLoad Data.
2. On the Load Data form, select Existing table.
3. In the Import set field, select Watershed Data \[sn_esg_watershed_data\].
4. Select Choose File, and select the file that you want to load.
5. Select Open.
6. In the Sheet number field, verify that the sheet number is appropriate.
7. In the Header row field, verify that the header row is appropriate.
8. Select Submit.

## Result

The spreadsheet is loaded in the staging table. All the columns from the spreadsheet
are created.

## What to do next

[View the
import set](https://servicenow-prod.fluidtopics.net/SBaTpcUp08cp_yVqOciqSw "Verify if your data is imported correctly from an external source. This verification enables you to identify if there were any errors during the data import.").