# Map a task template

# Associate a task plan template to a work schedule {#ariaid-title1}

* Freigeben Version: Australia
* 
* Aktualisiert 12. März 2026
* 
* ![](https://www.servicenow.com/docs/portal-asset/ico-clock) 1 Minute Lesedauer

Map a single or multiple task plan templates to a planned work schedule. Add conditions to identify the relevant templates for the planned work records.

## Vorbereitungen

Role required: sn_fsm_planned_wm.planned_work_admin

## Warum und wann dieser Vorgang ausgeführt wird

If you set the template type of a work plan to Task plan template, you can link its planned work schedules with task plan templates. For more information, see [Create a work plan](https://servicenow-prod.fluidtopics.net/dvHeakFpUyxL16WeD2ySPQ "Create a work plan to specify how and when the work should be performed for any activity.").

When the conditions specified in the planned work schedule template are met, tasks, cases, or incidents are created based on the defined task plan templates.
For example, to meet the monthly audit requirement of inspecting multiple stores of the same organization simultaneously, you need to create individual planned work schedules for each audit. Link each schedule to a different task plan template. Include relevant conditions in each planned work schedule template to ensure the correct template is applied when generating tasks specific to each audit.

## Prozedur

1. Navigate to AllField ServicePlanned Work ManagementPlans.
2. Open a plan from the list of work plans.
3. In the Planned Work Schedules related list, select a schedule to which you want to associate a task template.
4. In the Planned Work Schedule Task Templates related list, select New.
5. On the form, fill in the fields.  
   {#map-schedule-to-task-template__table_vxv_csf_25b__entry__2}

   | Field | Description |
   |-|-|
   | Template | Task plan template to be associated with the planned work schedule. For more information on the creation and usage of task plans, see [Task Plan Templates](https://www.servicenow.com/docs/access?context=task-plan-templates&version=australia&pubname=australia-customer-service-management&ft:locale=en-US). |
   | Schedule | Planned work schedule to which you're adding the template. This field is automatically set to the selected planned work schedule. |
   | Table | Table that is associated with the corresponding work plan of this planned schedule. This field is automatically set to the table name selected for the work plan. |
   | Condition | Filter conditions to determine the task plan template to be used to tasks based on the planned schedule. |
   [Tabelle : 1. Planned Work Schedule Task Template form]

   {#map-schedule-to-task-template__table_vxv_csf_25b}
6. Select Submit.
{#map-schedule-to-task-template__steps_psx_gc1_hhc}

## Ergebnisse

Task plan templates are linked to schedules, and when generating tasks for a specific work plan, the corresponding template is used.