# Task Dependencies for Task Plan Templates

# Task Dependencies for Task Plan Templates {#ariaid-title1}

Release version: Brazil  
Updated September 4, 2026  
![](https://www.servicenow.com/docs/portal-asset/ico-clock) 2 minutes to read
Summarize  
![AI sparkle icon](https://servicenow.com/docs/portal-asset/ai-sparkle-icon) Summarized using AI  
This content was generated using new OpenAI-powered functionality. Results are provided on an as is basis and are not guaranteed to be accurate or complete.  

## Summary of Task Dependencies for Task Plan Templates

Task dependencies in Task Plan Templates define the execution order between tasks, cases, and case tasks, enabling controlled sequencing within generated task records.
By establishing predecessor and successor relationships, these dependencies help tasks start at the appropriate time, reducing ambiguity for agents and improving workflow clarity.
Show full answer Show less  

## Key Features

* **Dependency Management:** Administrators and users with edit permissions can add or update task dependencies only when the template is in Draft state. Users with read-only access can view dependencies after the template is shared.
* **Storage and Interface:** All dependencies are stored in the Task Plan Template Dependency table and can be managed through list views, form views, and related lists on the template record.
* **Dependency Details:** Each dependency record includes predecessor and successor tasks, dependency type, minimum and maximum lag times, option to use maximum lag time, and assignment criteria such as "Same agent" or "Same day, same agent".
* **Dynamic UI:** UI policies dynamically show or hide fields, for example, showing the Maximum lag time field when the corresponding option is selected.
* **Validation and Security:** Built-in validations prevent circular, self-referencing, or duplicate dependencies. Role-based access controls restrict who can create, update, delete, or view dependencies based on user roles and template state.
* **Dependency Application:** The "Apply Template" action, available only after the template is published, generates task records and enforces defined dependencies between template items.
* **Business Organization Awareness:** When generating records across multiple business organizations, dependencies pair predecessor and successor tasks only within the same organization.
* **Cross-Table Dependencies:** Dependencies can link tasks across different target tables, such as a case task depending on a case, supporting flexible task sequencing.

## Practical Impact for ServiceNow Customers

By using task dependencies in Task Plan Templates, you can ensure predictable and clear task execution sequences that align with your business processes. This reduces confusion for agents and improves task coordination. The ability to manage dependencies with precise lag times and assignment rules enhances control over task timing and responsibility. Access controls and validations maintain data integrity and governance, while the dynamic UI simplifies dependency configuration. Applying a published template automatically generates and links tasks according to your defined dependencies, streamlining task plan deployment across your organization.  
Task dependencies define the execution order between tasks, case, and case tasks in a Task Plan Template.

Overview

Task dependencies provide controlled sequencing within the generated records from the template items in the Task Plan Template Dependency table. By defining predecessor and successor relationships, the tasks can
start at the correct time reducing ambiguity for agents. Administrators and users with edit permissions can add or update dependencies when the template is in the Draft state. Users with read‑only access can view
dependency information after the template is shared.

All dependency records are stored in the Task Plan Template Dependency table. Each record includes the predecessor, successor, dependency type, minimum and maximum lag times, use max lag time, and assignment
criteria.

The user interface provides list views, form views, and a related list on the template record to support dependency management. UI policies dynamically show or hide fields based on user selections. For example, selecting Use maximum lag time displays the Maximum lag time field, allowing users to specify the maximum lag duration.

The Assignment criteria field contains the drop‑down list with options such as Same agent and Same day, same agent. Built‑in validations prevent circular,
self‑referencing, or duplicate dependencies. Role‑based access controls determine who can view, create, update, or delete dependency records, depending on the user's role and the template state.


option.

Apply Template is available only after a task plan template is published. When selected, it generates task records in the corresponding tables and populates the defined dependencies between template items in the
Task Dependency table. Task plan template users and administrators can add, edit, or remove dependencies using the provided UI controls only when the template is in Draft state. When a
dependency is removed, the system displays a custom confirmation message indicating that only the dependent tasks are affected.

You define a dependency once, between two template items. When records are generated from a published task plan template, the dependency creates a pair between the corresponding predecessor and successor
records. When records are generated for multiple business organizations, a separate pair is created for each business organization: a predecessor is paired only with a successor that was generated for the same business organization,
never with a record generated for another business organization.

The predecessor and the successor do not need to be created in the same target table. Pairing works across target tables, such as a case task that depends on a case.

Task dependencies help ensure clear and predictable task sequencing and support multiple dependency types through minimum and maximum lag times.