Add task dependencies between template items
Add dependencies between template items in a task plan template to control the sequence in which tasks are available to agents after the template is applied.
Before you begin
Role required: sn_task_plan.viewer, sn_task_plan.navigation_menu, or sn_task_plan.admin
Plugin IDs: com.sn_task_plan_templates, com.snc.task_dependency, and com.snc.customerservice.demo.
Verify that the following conditions are met:
- The task plan template is in Draft state. You can add or edit dependencies only while the template is in Draft state.
- The template contains at least two template items to link as a predecessor and a successor.
About this task
Task dependencies define the order in which agents act on tasks generated from a task plan template. All tasks are created at the same time when the template is applied. Dependencies determine when a successor task is available based on the status of a predecessor task and any configured time constraints.
Dependencies control the order in which agents can act on those tasks after generation. You can set how strictly a dependency is enforced and add an optional time offset between tasks.
You can define the following dependency types, which determine when a successor task is set to active:
| Dependency type | When the successor task becomes active |
|---|---|
| Finish to start | The successor task is active after the predecessor task is completed. |
| Start together | The same scheduled time as the predecessor task. |
| Start after start | The predecessor task starts. |
Procedure
Edit or delete a dependency
Edit the fields of an existing dependency or remove it from the dependency map in a task plan template.
Before you begin
Role required: sn_task_plan.writer